In this article

The progress interface

The progress interface contains a detailed range of value metrics when updating progress.

You now have the ability to view progress as a value as well as a percentage and other progress figures when logging and tracking progress.  This means you can view the value of the work done in one place without the need to navigate to another page.

> Back to top

Viewing progress values

A. The cost for the item, in this example, is £2,292.38 per single item.

B. How much progress has been completed as a value figure.

For example: here, you can see that £1,719.29 worth of progress has been completed out of £2,292.38 which is the rate for the single item.

C. This is equal to 75% of the job.

D. Total rate as a value for the whole job, per single item.

E. Total value of the progress completed so far (blue figure) and total value of the entire job (black figure).

> Back to top