Fixed cost variations
Variations to project packages can also be requested for fixed costs as well as measured works.
Adding a fixed cost variation
- Expand the main Chalkstring black menu bar and click on the ‘Projects’ menu.
- Search for and click the 'Project' to add the variation to.
- Within the project homepage, click ‘Project hub’ sub menu.
- Click on the sub menu for work package where the variation is to be added.
- Click on the ‘Fixed costs’ sub menu.
- Select the fixed cost from drop-down menu. If the fixed cost you want to add isn't in the drop down, click ‘New Fixed Cost’ to add a new one. See article ‘Adding and editing fixed costs’ for further details on adding new fixed costs.
- Enter the quantity, period length and any profit for the fixed cost.
- Click save.
The new fixed cost will then appear in the fixed cost list. It will be identified as a variation by a blue variation icon.
The impact of the variation to the package price can be seen on the ‘assessment overview’.